September 10, 2024
8 photo
The suspended ceiling of the first floor has been covered with plasterboard. Finishing the floor of the first floor (terrazzo) has begun. Soundproofing of the immersion room has started. Concrete and waterproofing of underground tanks and the pump room have been completed.