January 25, 2025
5 photo
Installed 570 piles. The installation of the A5 building is 100% complete, and work on other sites continues. Excavation of the first stage was carried out at 58% of the total volume, 43144m³ were removed.
February 11, 2025
5 photo
January 7, 2025
4 photo