April 30, 2024
6 photo
Completed the driving of reinforced concrete piles for the building foundation to a depth of 11 meters. Completed the installation of reinforced concrete footings on top of the piles. Completed the concreting process for the footings. Works on the arrangement of reinforced concrete foundation beams have been completed. Engineering communications have been laid under the floor slab of the first floor. Waterproofing and backfilling of the foundations have been completed, and the reinforcement of the first floor slab has been finished as well. The first floor slab has been concreted. The two-storey metal columns have been assembled in their design position.