Request a call
0%

April 18, 2025

5 photo
A total of 1,348 piles have been installed at the Layan Verde construction site. Piling works for buildings A2.1, A4, and A5 are now fully completed. Excavation is ongoing, with 136,070 m³ of soil removed to date. Foundation pouring has begun at Building A5, where a time capsule was ceremonially placed together with our structural contractor, Westcon.