May 9, 2025
8 photo
Foundation construction is actively underway for buildings A5 and A2, along with drilling at A3 and preparation at ME1. A total of 155,720 m³ of soil has been removed from the site, and 1,408 piles have been drilled. The installation of the batching plant silos has been completed. Tower crane TC3 has been connected, and work continues on the second service road. The slopes have been reinforced for the rainy season, and additional drainage equipment has been obtained.