May 22, 2025

5 photo
A total of 1,434 piles have been installed at the Layan Verde construction site. Piling works for buildings A3.1, A2.2 and A3.2 is nearing completion. The excavation of the soil is continued, with 155,720 m³ of soil removed. Work continues on the pouring of the foundations and framing structures of the buildings for the first stage, with a total volume of 557 m³ having been completed. A batching plant has been installed and partially filled with cement. Work is currently underway on its water and electricity supply systems. The installation of drainage equipment has been completed.