June 12, 2025

6 photo
A third tower crane has been installed at the construction site and put into operation. Testing of piles for phases 2 and 3 of the project is ongoing.The foundation work for Building A5 is 100% completed. Zone 2 is ready for pouring the first slab and concreting has begun. Installation of piles for Buildings A3.1, 3.2, A4 has been completed. The foundation work for Building A2.2 is 50% completed, and for Building A2.1 is 80%.