May 11, 2026

7 photo
A total of 2,093 piles are installed at the Layan Verde construction site. Soil excavation continues, with 339,060 m³ removed to date. Engineering works are in progress in Building A5, along with installation of internal partition walls on the 2nd, 3rd, and 5th floors. Formwork installation and reinforcement works continue for the 6th floor of Building A2.1, while scaffolding installation is underway for the 3rd-floor slab of Building A2.2. Installation of vertical structural elements continues on the 2nd floor of Building A3.1. In Building A4, formwork installation and reinforcement works are underway for the 5th floor in Zone 1. Foundation works continue in Building B8, along with pile installation works in Building B3. A total of 21,073 m³ of concrete is placed for foundations and structural frame elements.