Completed the installation of the skylight glazing. Work on the priming and painting of the steel spiral staircase has continued, and the wooden facade on the second floor has been completed. The work on the first floor facade has also begun. Installation of wooden decking on the terrace has started, and the terrazzo skirting boards on the second floor have been installed, as well as the floor tiles. The installation of track rails for lighting fixtures has begun. Terrazzo installation on the first floor (sanding) is continuing.