50 piles were installed and 1,500m³ of soil was removed. It is planned to install 80 piles per week and excavate 5,000m³ of soil. Work continues on clearing the area for future works, constructing temporary and permanent roads, installing drainage system, and building temporary structures: fencing, wheel washing areas, construction offices.