July 30, 2025

7 photo
As of today, the total volume of structural concrete poured has reached 2,716 m³. At Building A5, column installation for the second floor continues in Zone 1, concrete pouring for the third floor has been completed in Zone 2, and the second floor slab for the post-tensioning system is installed in Zone 3. Foundation and water tank structure works are progressing parallel at Buildings A2.1 and A2.2. At Building A3.1, pile cutting and foundation works are ongoing. Drilling has started in zone BM2.