September 30, 2025

5 photo
As of today, the total volume of structural concrete poured has reached 3,881 m³. In Building A5, column construction for the 4th floor in Zone 1 continues; the floor slab of the 5th floor in Zone 2 has been poured; and scaffolding installation for the 4th floor slab in Zone 3 is in progress. Foundation and water tank structure works are ongoing for both Building A2.1 and Building A2.2. Foundation works also continue in Building A3.1.