October 21, 2025
5 photo
In Building A5, the floor slab of the 5th floor in Zone 1 has been poured; the construction of the columns on the 5th floor of zone 2 and 4th floor of zone 3 is ongoing. Foundation and structural works for the water reservoirs are nearing completion for Buildings A2.1 and A2.2. Building A3.1 foundations work continues. A total of 4,806 m³ of foundations and structural frame elements have been cast.