October 31, 2025

6 photo
As of today, the total volume of structural concrete poured has reached 4,925 m³. In Building A5, the construction of the columns on the 5th floor of zone 1 and 2 is ongoing; the installation of scaffolding to cover the 5th floor of zone 3 is underway. Waterproofing works for the foundations of Buildings A2.1 and A2.2 are in progress. Foundation works for Building A3.1 and A4 are in progress.