January 14, 2026
7 photo
A total of 1,827 piles are installed at the Layan Verde construction site. Soil excavation continues, with a cumulative volume of 281,180 m³ removed. Installation of internal partition walls continues on the 2nd and 3rd floors of Building A5. Scaffolding installation is underway for the 3rd-floor slab of Building A2.1 and for the 4th-floor slab of Building A2.2. Installation of vertical structural elements continues in Building A3. In Building A4, the 2nd-floor slab in Zone 2 is cast. Foundation works for Building B8 continue. A total of 9,514 m³ of concrete is placed for foundations and structural frame elements.






