February 14, 2026
5 photo
A total of 1,876 piles are installed at the Layan Verde construction site. Soil excavation continues, with a cumulative volume of 308,650 m³ removed. Installation of internal partition walls is underway on the 3rd and 4th floors of Building A5. In Building A2.1, formwork installation and reinforcement works are in progress for the 4th floor, along with scaffolding installation for construction of the 5th-floor slab of Building A2.2. Scaffolding installation continues for construction of the 1st-floor slab (Zone 1) of Building A3.1. Formwork installation and reinforcement works continue for Zone 1 of the 1st floor of Building A4. Foundation works continue in Building B8. A total of 10,982 m³ of concrete is placed for foundations and structural frame elements.




