February 27, 2026

5 photo
The total volume of placed structural concrete stands at 12,094 m³. Soil excavation continues, with 318,950 m³ removed to date, and a total of 1,927 piles installed. Installation of internal partition walls continues on the 3rd and 4th floors of Building A5. In Building A2, scaffolding installation is underway for construction of the 5th-floor slab. In Building A3.1, formwork installation and reinforcement works for the 1st floor continue, while in Building A3.2 installation of vertical structural elements is underway on the foundation slab. In Building A4, formwork installation and reinforcement works are in progress for the 4th floor (Zone 2), along with installation of vertical structural elements on the foundation slab in Zone 1. Foundation works continue for Building B8.