March 16, 2026
8 photo
A total of 1,955 piles are installed at the Layan Verde construction site. Soil excavation continues, with 324,606 m³ removed to date. Engineering works continue on the 3rd and 4th floors of Building A5. In Building A2.1, the 5th-floor slab is cast, and formwork installation and reinforcement works continue for the 5th floor of Building A2.2. Installation of vertical structural elements continues on the 4th floor (Zone 2) of Building A4. In Building A3.1, formwork installation and reinforcement works for the 1st floor continue, while in Building A3.2 scaffolding installation is underway for construction of the 1st-floor slab. Foundation works continue for Building B8, along with active pile installation works for Building B3. A total of 13,522 m³ of concrete is placed for foundations and structural frame elements.