March 30, 2026
4 photo
The total volume of placed structural concrete stands at 15,176 m³. Soil excavation continues, with 332,366 m³ removed to date, and a total of 1,989 piles installed. Engineering works continue in Building A5. Installation of vertical structural elements continues on the 5th floor of Building A2.1. In Building A2.2, the 5th-floor slab is cast. Installation of vertical structural elements continues on the 1st floor of Building A3.1, along with formwork installation and reinforcement works for the 3rd floor (Zone 1) of Building A4. Foundation works continue for Building B8, along with active pile installation works for Building B3.