April 10, 2026

7 photo
A total of 2,008 piles are installed at the Layan Verde construction site. Soil excavation continues, with 336,310 m³ removed to date. Engineering works are in progress in Building A5. In Buildings A2.1 and A2.2, installation of vertical structural elements continues on the 5th floor, while in Building A3.1 works continue on the 1st floor. In Building A4, formwork installation is underway for the 5th floor (Zone 2), along with installation of vertical structural elements for the 3rd floor (Zone 1). Foundation works continue in Building B8, along with pile installation works in Building B3. A total of 15,576 m³ of concrete is placed for foundations and structural frame elements.