June 2, 2026

9 photo
The total volume of placed structural concrete stands at 21,874 m³. Soil excavation continues, with 339,060 m³ removed to date, and a total of 2,120 piles installed. Engineering works and installation of internal partition walls continue on the 3rd, 4th, and 5th floors of Building A5. In Building A2.1, the 6th-floor slab is cast, while formwork installation and reinforcement works for the 3rd floor continue in Building A2.2. The same works are in progress on the 3rd floor of Building A3.1. In Building A4, the 5th-floor slab in Zone 1 is cast. Foundation works continue for Buildings A1 and B8, along with pile installation for Building B3.