June 16, 2026

8 photo
A total of 2,160 piles are installed at the Layan Verde construction site. Soil excavation continues, with 339,060 m³ removed to date. Engineering works, installation of internal partition walls, and plastering works are in progress in Building A5. Formwork installation and reinforcement works continue for the roof slab of Building A2.1 and the 3rd floor of Building A2.2. Formwork installation and reinforcement works are underway for the 3rd floor of Building A3.1, while foundation works continue for Building A3.2. Formwork installation and reinforcement works continue for the roof slab in Zone 1 of Building A4. Foundation works continue in Buildings A1 and B8, along with pile installation works in Building B3. A total of 23,071 m³ of concrete is placed for foundations and structural frame elements.