June 29, 2026

7 photo
The total volume of placed structural concrete stands at 24,098 m³. Soil excavation continues, with 339,060 m³ removed to date, and a total of 2,195 piles installed. In Building A5, the installation of interior partition walls is underway on the 3rd floor. In Building A2.1, the pouring of the roof slab has been completed, while in Building A2.2, the construction of the 3rd-floor slab continues. Scaffolding erection is in progress for the 4th-floor slab of Building A3.1. Foundation works are underway for Buildings A3.2, A1, B8, and B9.