July 20, 2026
7 photo
A total of 2,228 piles are installed at the Layan Verde construction site. Installation of internal partition walls continues on the 4th and 5th floors of Building A5. In Building A4, installation of water supply, sanitary drainage, and fire protection systems has commenced. In Building A2.2, formwork installation and reinforcement works are underway for the 2nd floor in Zone 1, while the 6th-floor slab is cast in Zone 2. Formwork installation and reinforcement works continue for the 4th floor of Building A3.1. Foundation works are underway in Buildings A3.2, A1, B8, and B9. A total of 25,257 m³ of concrete is placed for foundations and structural frame elements.