April 10, 2025
6 photo
Active preparations for structural works are underway at the construction site. Soil excavation totaling 133,890 m³ has been completed, and 1,331 piles have been installed. Piling work for Building A4 is 100% complete. A tower crane has been installed, and the foundation for another tower crane has been poured. For Building A5, rebar has been placed and the first concrete foundation has been poured.