June 27, 2025
5 photo
In Building A5, the second-floor slab has been cast in Zone 2; slab casting for the first floor is in progress in Zone 1. Installation of the underground drainage pipe has been completed in Zone 3. Foundation casting is ongoing for Buildings A2.1 and A2.2. A total of 1,557 m³ of foundations and structural frame elements for the Phase 1 buildings have been cast to date. Pile head trimming and blinding layer preparation are underway in Building A3.1 in advance of raft foundation casting. Excavation works are in progress for Buildings BM1 and A3.1. All temporary water reservoirs are fully operational and prepared for the rainy season.