August 21, 2025
5 photo
Last week, the first pile of Phase 2 was cast. This week, drilling and installation of new piles for Building B8 are underway. In Building A5, concrete has been cast for the 4th floor in Zone 2, while formwork installation for the 3rd floor is in progress in Zone 3. Foundation and structural works for the water storage tanks are being carried out concurrently at Buildings A2.1 and A2.2. At Building A3.1, pile head trimming and foundation construction continue. Public drainage infrastructure works are in progress. To date, a total of 3,051 m³ of concrete has been cast.