September 17, 2025
6 photo
As of today, the total volume of structural concrete poured amounts to 3,704 m³. In Building A5, the floor slab of the 4th floor in Zone 1 has been poured; scaffolding installation for the 5th floor slab in Zone 2 is in progress; and column construction for the 3rd floor in Zone 3 continues. Foundation and water tank structure works are ongoing for both Building A2.1 and Building A2.2. Foundation works also continue in Building A3.1. Pile installation in Building B8 is completed at 54%.