April 27, 2026
9 photo
The total volume of structural concrete poured stands at 16,285 m³. Soil excavation continues, with 339,060 m³ removed to date and 2,042 piles installed. In Building A5, engineering works and the installation of interior walls on the 2nd and 3rd floors are in progress. The installation of vertical structures continues at the rear of Building A2.1 and on the 5th floor of Building A2.2. Formwork and reinforcement for the 2nd floor in Zone 1 of Building A3.1 are ongoing, while the 2nd-floor slab in Zone 2 has been poured. The installation of scaffolding to cover the 1st floor in building A3.2 is underway. In Building A4, formwork and reinforcement for the 4th floor in Zone 1 are underway, and the 5th-floor slab in Zone 2 has been poured.