31 серпня 2024 р.
10 фото
Completed the installation of external air conditioning units on the roof and preparation of internal walls for underpainting. Assembled the spiral metal staircase and began work on painting. Poured the screed with a slope on the terrace and applied penetrating waterproofing. Installed glazing on the facade of the building and installed internal glass partitions. Started tiling the walls of the bathrooms and shower room. Applied decorative sandwash coating to the facade and started installation of the suspended ceiling support frame.