December 15, 2025
5 photo
A total of 1,810 piles are installed at the Layan Verde construction site. Soil excavation works continue, with 259,430 m³ removed to date. Installation of plumbing pipelines has commenced in Building A5. Scaffolding installation is underway for the 2nd-floor slab of Building A2.1, and partial casting of the 2nd-floor slab of Building A2.2 is complete. Foundation works continue for Buildings A3, A4, and B8. In Building BM2, foundation construction and slab reinforcement works are ongoing. A total of 7,430 m³ of concrete has been placed for foundations and structural frame elements.