February 2, 2026

4 photo
The total volume of placed structural concrete stands at 10,329 m³. Excavation works are ongoing, with a total of 299,270 m³ of soil removed. Installation of internal partitions continues on the 3rd and 4th floors of Building A5. Work is underway to install scaffolding for the 3rd floor slab of Building A2.1. In Building A2.2, the 4th floor slab has been partially poured. The pouring of the basement slab in Building A3.2 has been completed, and in Building A4, the 3rd floor slab has been poured. Foundation works for Building B8 are also ongoing.