Construction progress
Video progress

February 3, 2026
299,270 m³ of soil excavated, 1,858 piles drilled, and 10,329 m³ of concrete poured. In building A5, wall masonry continues on the 3rd and 4th floors, and MEP installation from the 1st to 5th floors. In A2.1, vertical structures are being erected on the 3rd floor, and in A2.2 post-tensioned reinforcement has been installed for the 4th floor slab, with concreting (130 m³) scheduled for tomorrow. In A3, vertical structure work continues. In A4 (zone 2), the 3rd floor slab concreting is complete (100 m³). In BM2 (zone 1), scaffolding is being installed for the next floor. In B8, foundation work is ongoing. In the second phase, earthworks and soil removal continue in zones BM5 and BM4.
See more

January 20, 2026
286,780 m³ of soil excavated, 1,835 piles drilled, and 9,746 m³ of concrete poured. In building A5, planter boxes and pool work continues on the 5th floor, wall masonry on the 3rd and 4th floors, and MEP installation from the 1st to 5th floors. In A2.1, the 3rd floor slab is being reinforced, and in A2.2 the 4th floor slab. In A3 and BM2 (zone 1), vertical structures are being erected. In A4, vertical structure work continues on the 2nd floor in zone 2, and foundation work in zone 1. In B8, foundation work is ongoing. In the second phase, earthworks and soil removal continue in zones BM5 and BM4, with pile drilling underway for building BM5.
See more

January 3, 2026
In building A5, planter boxes and pools are being installed on the 5th floor, while wall masonry continues on the 2nd and 3rd floors. In A2.1, the 2nd floor slab has been completed, and in A2.2 the 3rd floor slab is being poured. In A3, work continues on beams and the 2nd floor slab. In A4, formwork for the 2nd floor slab is being installed and columns are being erected. In B8, additional pile installation is complete and foundation work is underway.
See more

December 22, 2025
In building A5, plumbing and pool work continues on the 5th floor, and wall masonry is underway on the 3rd floor in zone 3. In A2.1, the 1st floor slab has been poured, with reinforcement and sleeve pipe installation continuing for the 2nd floor slab. In A2.2, the 2nd floor slab is partially poured, formwork is being installed for the 3rd floor, and 1st floor vertical structures are being erected. In A3, foundation, beam and slab work continues. In A4, the 1st floor slab is partially poured, with foundation work ongoing on the other section. In BM2, 650 m³ of concrete was poured today for the 1st floor slab, and hard material excavation is on hold. At Chockchai, leveling work continues to prepare drilling platforms for BM5 and BM4. In B8, foundation work is ongoing. Excavation work actively continues at phase 2.
See more

December 1, 2025
245,320 m³ of soil has been excavated and 1,777 piles have been installed. In building A5 B (zones 1, 2, and 3), the roof slab has been poured, and the installation and testing of the passenger elevator continues. In buildings A2.1 and A2.2, work on the first-floor slabs is underway. In buildings A3.1 and A4, foundation work continues. In building B9, active piling work is in progress.
See more

November 3, 2025
At Building A5, all three zones continue with column reinforcement installation and formwork setup for the 5th-floor slab. In Buildings A2.1 and A2.2, foundation and water tank works are nearing completion, and waterproofing is in progress. Building A3.1 continues with foundation and beam construction, while foundation works have started at A4. In zone BM2, excavation of hard materials is ongoing across three areas. On Phase 2, piling for Buildings B8–B9 continues, and the box culvert drainage system is being installed along the road. To date, 237,860 m³ of soil have been excavated, 1,667 piles drilled, and 5,162 m³ of concrete poured.
See more

October 24, 2025
At Building A5, all three zones continue with column reinforcement installation and formwork setup for the 5th-floor slab. In Buildings A2.1 and A2.2, foundation and water tank works are nearing completion, and waterproofing is in progress. Building A3.1 continues with foundation and beam construction, while foundation works have started at A4. In zone BM2, hard material excavation is ongoing in areas 1, 2, and 3. Phase 2 piling works for Buildings B8–B9 are in progress, the installation of the box culvert drainage system continues, and construction works are underway on the south servitude road.
See more

October 8, 2025
At Building A5, reinforcement for the roof columns is being installed, scaffolding and formwork are in place for the 5th-floor slab, and concreting of the 4th floor has been completed. Buildings A2.1 and A2.2 continue with foundation, water tank, and waterproofing works, while A3.1 progresses with foundation and beam installation. In zone BM2, excavation of hard material is underway. Along the project frontage, installation of the box culvert drainage system has begun. On Phase 2, piling works for Buildings B8–B9 continue, with two rigs operating simultaneously.
See more

September 27, 2025
In building A5, the crew is installing column reinforcement on the 4th floor, completing preparations for concreting the 5th-floor slab, and pouring concrete for the 3rd-floor columns. In buildings A2.1/A2.2, work is ongoing on the foundations, water tanks, and waterproofing, while in A3.1, the construction of the foundation and beams continues. To date, 1,557 piles have been drilled and 3,881 m³ of concrete has been poured.
See more

September 17, 2025
As of today, the total volume of structural concrete poured amounts to 3,704 m³. In Building A5, the floor slab of the 4th floor in Zone 1 has been poured; scaffolding installation for the 5th floor slab in Zone 2 is in progress; and column construction for the 3rd floor in Zone 3 continues. Foundation and water tank structure works are ongoing for both Building A2.1 and Building A2.2. Foundation works also continue in Building A3.1. Pile installation in Building B8 is completed at 54%.
See more

August 30, 2025
August 30, 2025 As of today, the total volume of structural concrete poured has reached 3,402 m³. The installation of columns in building A5 continues in zones 1 and 2, while the installation of formwork and reinforcement is ongoing in zone 3. Foundation and structural works for the water storage tanks are being carried out concurrently at Buildings A2.1 and A2.2. Foundation and beam filling work has started in building A3.1. Drilling and installation of piles for Building B8 are underway.
See more

August 21, 2025
August 21, 2025 Last week, the first pile of Phase 2 was cast. This week, drilling and installation of new piles for Building B8 are underway. In Building A5, concrete has been cast for the 4th floor in Zone 2, while formwork installation for the 3rd floor is in progress in Zone 3. Foundation and structural works for the water storage tanks are being carried out concurrently at Buildings A2.1 and A2.2. At Building A3.1, pile head trimming and foundation construction continue. Public drainage infrastructure works are in progress. To date, a total of 3,051 m³ of concrete has been cast.
See more

July 30, 2025
July 30, 2025 As of today, the total volume of structural concrete poured has reached 2,716 m³. At Building A5, column installation for the second floor continues in Zone 1, concrete pouring for the third floor has been completed in Zone 2, and the second floor slab for the post-tensioning system is installed in Zone 3. Foundation and water tank structure works are progressing parallel at Buildings A2.1 and A2.2. At Building A3.1, pile cutting and foundation works are ongoing. Drilling has started in zone BM2.
See more

July 17, 2025
July 17, 2025 As of the reporting date, a total of 188,620 m³ of soil has been excavated and 2,226 m³ of concrete has been cast. Significant progress has been made on Building A5: In Zone 1, formwork and reinforcement installation for the second floor is ongoing; In Zone 2, formwork installation for the third floor is in progress; In Zone 3, the first-floor slab has been cast, and column installation has commenced. Foundation and structural works for the water storage tanks are underway for both Buildings A2.1 and A2.2. At Building A3.1, pile head trimming and foundation construction are in progress. Earthworks continue in the areas of Buildings BM1 and BM2.
See more

June 30, 2025
June 30, 2025 In Building A5, first and second-floor slab casting has been completed in Zone 2. Foundation works are ongoing in Building A2. Pile head trimming and blinding layer preparation are in progress in Building A3.1 in advance of raft foundation casting. A total of 1,738 m³ of concrete poured for foundations and structural frame elements of the Phase 1 buildings. Excavation activities are ongoing, with the total volume of excavated soil reaching 177,900 m³.
See more

May 27, 2025
May 27, 2025 Construction at Layan Verde is progressing actively. A total of 159,430 m³ of soil has been removed and 1,440 piles installed. Concrete pouring is underway, with 534 m³ poured into Building A5 and 228 m³ into Building A2. The installation of drainage pumps has been completed, preparing the site for the rainy season. The project is advancing on schedule.
See more

April 6, 2025
April 6, 2025 In March, we completed the removal of 124,780 m³ of soil and installed 1,282 piles. To protect the construction site during the rainy season, a temporary drainage system was installed. Temporary transformers were connected to ensure an uninterrupted power supply. The structural contractor, Westcon, has already started work: construction of the foundation for Building A5 is underway, tower crane TC4 has been installed, and the first pile cap has been poured.
See more

March 20, 2025
March 20, 2025 Installed 1234 piles. The excavation of the soil is continued, with 111,320 m³ of soil removed. The tender for construction work on the Layan Verde project has been completed. Westcon, a reliable contractor with a proven track record of large-scale projects in Phuket, has been selected as the winner.
See more

March 3, 2025
March 3, 2025 We sum up the February 2025 results. Work is heating up on the construction site: 87,510 m³ of soil has already been removed, and 1,080 piles have been installed. The A5 building’s pile installation is fully complete, while the A4 building’s pile installation is 91% finished. We have also received official building permits for all phases.
See more

February 3, 2025
February 20, 2025 The installation of piles has been completed by 41%, with a total of 909 piles installed. The installation of piles in A5 building is 100% complete. The total volume of soil removal has reached 20%, with 74,480 m³ of soil excavated. In Phase 1A, excavation is 95% complete.
See more
January 17, 2025
The installation piles of the first stage were completed by 38%. The installation of piles in A5 building is 98% complete. 453 piles have been installed in general. The total volume of soil removal, which amounts to 33794m³, has been achieved by 46%.
See more

December 3, 2024
50 piles were installed and 1500m³ of soil was removed. It is planned to install 80 piles per week and excavate 5000m³ of soil. Work continues on clearing the area for future works, constructing temporary and permanent roads, installing drainage system, and building temporary structures: fencing, wheel washing areas, construction offices.
See more

November 16, 2024
The Sales Office opened door. The main construction work is completed
See more

November 12, 2024
The Sales Office is undergoing final preparations. Planted green belt in the area, tested equipment, and prepared the premises.
See more

November 6, 2024
Сontinuе to build the Sales Office. Converted the open terrace: installing wooden coverings, the electricity.
See more

October 30, 2024
Continue final works: clean finishing and improvement of the surrounding area. Perform commissioning works of engineering equipment.
See more

September 27, 2024
Continue drilling test piles for second and third round
See more

July 9, 2024
Completing the installation of guides for internal glass walls. Continue Installation of internal engineering systems (ventilation, air conditioning, electrical, and low-current networks), working on the erection of internal walls.
See more